Our Aerospace client in Indianapolis, IN needed to remove from service existing underground fuel piping and replace it with new aboveground piping.
The Project scope was to disconnect existing underground fuel piping from fuel pumps located within fuel pits, thus removing underground fuel piping from service. Piping drawings were then prepared to show new tie-in details at pumps within the fuel pits and new aboveground routing of fuel lines to tie-ins within existing building test cells. Material specifications and support locations for new fuel piping were also included on drawings. Structural drawings for details regarding piping supports were also included.
Dynamic Engineering Design provided contractor bid packages that included design drawings, material specifications, bid forms, written scope of work, safety requirements, commercial aspects, schedule requirements, and general client requirements.